MCC vs PCC panel: what's the difference and which do you need?

A PCC distributes power to big feeders; an MCC starts, stops and protects motors. How they differ and how they fit together on an industrial site.

Poweramps engineering team · · 3 min read

Motor control centre (MCC) panel with individual motor feeders

On most factory, water-plant and building projects you will see both terms in the single-line diagram: a PCC near the transformer and one or more MCCs around the plant. They are both LT (low-tension) switchboards and can look similar from the front, but they do different jobs.

The short answer

  • A PCC (power control centre) receives power from the transformer and/or DG set and distributes it to large outgoing feeders: MCCs, lighting and power distribution boards, HVAC panels, capacitor panels.
  • An MCC (motor control centre) receives power from the PCC and controls and protects individual motors, each with its own starter feeder.

Think of the PCC as the main road junction and the MCC as the set of driveways to each machine.

Side-by-side comparison

PCC (power control centre) MCC (motor control centre)
Main job Receive and distribute bulk power Start, stop and protect motors
Fed from Transformer, DG set, or both The PCC (or a main distribution board)
Typical incomer ACB (air circuit breaker), sometimes with DG changeover ACB or MCCB
Typical outgoing feeders ACBs and MCCBs to sub-panels and large loads Motor feeders: breaker or MPCB, contactor, overload relay, plus starter
Busbar rating High: often thousands of amps Lower than the upstream PCC
Metering Incomer metering, often power-quality metering, sometimes APFC Ammeter and run/trip indication per motor
Controls Few: mostly switching and protection Many: push buttons, selector switches, interlocks, PLC signals

What goes into an MCC feeder

Each motor gets its own feeder, sized to the motor. A typical feeder has:

  1. Short-circuit protection: an MPCB or MCCB.
  2. Switching: one or more contactors.
  3. Overload protection: a thermal or electronic overload relay (or a motor protection relay on larger motors).
  4. The starter arrangement: DOL for small motors, star-delta for medium motors, soft starter or VFD where a smooth start or speed control is needed.
  5. Indication and control: ON/OFF/TRIP lamps, start/stop buttons, Auto/Manual selector, and terminals for remote or PLC control.

Because motors are spread across a plant, MCCs are often placed close to the loads they serve to keep cable runs short.

What goes into a PCC

A PCC is built around high current and high fault level:

  • Incomers from the transformer and DG, usually ACBs, with interlocking so the two sources are never connected together by mistake.
  • Main busbars rated for the full site load and the prospective short-circuit current.
  • Outgoing feeders to each MCC, PDB and large load.
  • Metering on the incomer, and often an APFC (automatic power factor correction) panel connected alongside.

Form of separation

Both PCCs and MCCs are specified with a form of separation under IS/IEC 61439: from Form 1 (no internal barriers) through Forms 2, 3 and 4 (progressively more separation between busbars, functional units and terminals). A Form 3b or Form 4 MCC lets maintenance staff work on one feeder while the rest of the plant keeps running. That matters on continuous-process sites, but it costs more space and money. Specify what your operation actually needs.

Which do you need?

  • Small site, a handful of motors: a single PMCC, one panel with an incomer, distribution and motor feeders, is usually the most economical.
  • Medium to large site: a PCC at the transformer room feeding separate MCCs near each process area, plus lighting and power distribution boards.
  • Adding machines to an existing plant: usually a new MCC fed from a spare feeder on the existing PCC. Check the PCC has the spare capacity and fault rating first.

How we can help

We build MCCs with DOL, star-delta, soft-starter and VFD feeders, and distribution panels with busbars up to 6300 A, at our works in Bengaluru. Every panel is factory tested before dispatch. To get a price, list your motors in our online panel builder or send us your SLD through the contact page.

See also: MCC panels · power distribution panels · LT panels

Questions

Frequently asked

Can one panel be both a PCC and an MCC?

Yes. On smaller sites a single PMCC (power and motor control centre) combines the incomer and distribution section with motor starter feeders in one line-up.

Which comes first in the power chain, PCC or MCC?

The PCC. It takes power from the transformer or DG and feeds the MCCs, distribution boards and other large loads downstream.

What starters can an MCC feeder have?

Direct-on-line for small motors, star-delta for medium motors, and soft starters or VFDs where you need a smooth start or speed control. One MCC can mix all of these.

What is form of separation in an MCC or PCC?

It describes how the inside of the panel is divided by barriers, from Form 1 (no internal separation) to Form 4 (busbars, every functional unit and its terminals separated). Higher forms let you work on one feeder while others stay live.